Client

BHP Billiton, Kwinana Nickel Refinery

Location

Kwinana, Western Australia

Project

G2D – 30 Tank Reduction Area

Work carried out:

Safely change out the floor in the limited time allocated during a major shutdown, including project management and supervision of miscellaneous contractors.

Activities

  • Installation of new access door and Tank Floor Replacement – 304 stainless steel material